Modernising an existing station is harder than building a new one, because the site usually has to keep operating and because what is already buried there is not always documented.
Survey before scope
Tank condition, buried services and the state of the containment system decide what the project actually is. A scope written before that survey tends to change once work starts, which is the most common source of dispute on this kind of job.
Phasing around trading
If the station stays open, the work is divided so that some dispensers keep operating while others are isolated. That requires physical separation of the work area, controlled vehicle routing and clear agreement on what happens if a phase overruns.
Bringing an older site up to current requirements
A station built to earlier requirements may need changes to containment, drainage or vapour handling as part of the upgrade. Establishing early which of these apply avoids discovering them at inspection, when the site is already part-dismantled.
This is also the moment to decide what is genuinely worth keeping. Reusing sound tanks or an intact forecourt slab saves real money, but only where their condition has been verified rather than assumed from their appearance.
Reopening
Commissioning an upgraded station means testing what was replaced and re-proving what was kept, then obtaining the approvals the changes call for. Planning the reopening as a defined stage, with the checks listed in advance, keeps it from becoming an open-ended tail at the end of the job.